Project

The 15-year-maturity loan totalling EUR 20 million has been provided for the construction of a 170-kilometre electricity interconnection between Estonia and Finland, Estlink 2. The new link will be the second power bridge between the Baltic countries and the Nordic region.

Of the entire length of the cable, 145 kilometres will be laid as a sea cable on the sea bed, 14 kilometres as an overhead line in Finland and 11 kilometres as a land cable in Estonia. Once the new 650 MW link is in operation in 2014, the capacity of the interconnection between Estonia and Finland will increase up to 1000 MW. The increase of the transmission capacity is one of the preconditions for the integration of the future power market between the Baltic countries and Nord Pool Spot.

Fingrid, established in 1996, is the sole national electricity transmission system operator in Finland. The company owns the Finnish main grid and all the significant cross-border connections. Currently, Fingrid has approximately 14,000 kilometres of transmission lines and 106 substations. Fingrid is responsible for the transmission of electricity in Finland and for maintaining and developing the infrastructure relating to transmission of electricity. Fingrid is owned by Fortum Power and Heat Oy (25%), Pohjolan Voima Oy (25%), the Republic of Finland (12%) and institutional investors (38%).

Sustainability summary

The main environmental impacts of the project will occur during the construction phase. These are mainly related to the underwater cable laying process, which may cause limited and temporary changes in the sea environment. Fingrid Oyj has an Environmental Management System for the project.

Press release
20.10.2010

NIB allocates EUR 45 million for Estlink-2

Press release

NIB lainaa 45 miljoonaa euroa Estlink-2:n rakentamiseen

Related resources

Article

9.12.2010

Estlink-2 to tie Baltic power producers closer to the Nordic markets